Step 1: Open the Compliance Event fromt he Vendor Record under the QC & Compliance subtab.
Step 2: Update the following fields in the Event section as needed.
Status
- Completed
- In Progress
- On Hold
- Scheduled
Renewal Status
- This drives the component testing reminders
- Current – after the component testing is complete
- Expired – after the component testing expires
- In Progress – when the component testing is in progress
Note
Step 3: Update the following fields in the Details section as needed.
Frequency
- When the component testing should be performed again.
Expiration Date
- When the component testing will expire
Step 4: Click Save
Step 5: Utilize the Drage & Drop feature to upload any documents, emails, etc.